Edexcel IAL · Mathematics · WDM11 · Critical path analysis

Topic Questions: 4.4 Total float. Gantt (cascade) charts. Scheduling. — WDM11 Critical path analysis

43 WDM11 Critical path analysis topic questions are tagged to this syllabus point across 15 papers (2020–2026). Only the parts whose knowledge graph matches this syllabus statement are counted, and the table shows which parts of each question are involved.

43 topic questions 15 papers 114 tagged marks 43.9% of topic questions 41.9% of topic marks 2020–2026 Syllabus 2018–current

Core finding

This Critical path analysis syllabus point appears in 15 WDM11 papers across 2020–2026, contributing 43 topic questions and 114 marks. The most recent appearance is WDM11/01 January 2026. That equals 43.9% of the 98 topic questions and 41.9% of the 272 marks tagged to Critical path analysis. Only parts tagged to this subtopic are counted, so a four-part question can contribute one item and one part's marks. The table lists every matching question, its tagged parts and marks, with a link back to the paper page. Sessions are newest first, so the statement can be traced back through the full paper history.

Topic questions by session

Newest sessions first. Parts and marks count only the parts tagged to this subtopic; “x of y parts” shows how much of the question is tagged elsewhere. Select the paper cell to open the matching question on the paper page, or use Go to Practice Hub to answer that exact question in the Interactive Practice Hub.

PaperQuestionTypePartsMarksDifficultyPractice
WDM11/01January 2026 · Edexcel IAL Q7
Critical Path Analysis - Edexcel IAL D1 Jan 2026 Q7
FRQ 2 of 5 parts ((d), (e)) 6
of 14 on the paper
Easy Go to Practice Hub
WDM11/02January 2026 · Edexcel IAL Q6
Critical Path Analysis and Gantt Charts - Edexcel IAL D1 Jan 2026 Q6
FRQ 3 of 5 parts ((c), (d), (e)) 9
of 14 on the paper
Easy Go to Practice Hub
WDM11/01June 2025 · Edexcel IAL Q7
Critical Path Analysis - Edexcel IAL D1 2025 Q7
FRQ 3 of 5 parts ((c), (d), (e)) 9
of 16 on the paper
Easy Go to Practice Hub
WDM11/01January 2025 · Edexcel IAL Q7
Critical Path Analysis - Edexcel IAL D1 2025 Jan Q7
FRQ 3 of 6 parts ((d), (e), (f)) 8
of 14 on the paper
Medium Go to Practice Hub
WDM11/01June 2024 · Edexcel IAL Q2
Critical Path Analysis - Edexcel IAL D1 2024 Q2
FRQ 2 of 4 parts ((b), (c)) 5
of 10 on the paper
Easy Go to Practice Hub
WDM11/01June 2024 · Edexcel IAL Q6
Activity Networks and Scheduling - Edexcel IAL D1 2024 Q6
FRQ 2 of 4 parts ((c), (d)) 4
of 10 on the paper
Medium Go to Practice Hub
WDM11/01January 2024 · Edexcel IAL Q1
Critical Path Analysis - Edexcel IAL D1 Jan 2024 Q1
FRQ 4 of 5 parts ((b), (c), (d), (e)) 9
of 13 on the paper
Easy Go to Practice Hub
WDM11/01June 2023 · Edexcel IAL Q1
Project Activity Network - Edexcel IAL D1 June 2023 Q1
FRQ 3 of 4 parts ((b), (c), (d)) 6
of 10 on the paper
Easy Go to Practice Hub
WDM11/01January 2023 · Edexcel IAL Q4
Critical Path Analysis - Edexcel IAL Decision Mathematics D1 Jan 2023 Q4
FRQ 3 of 6 parts ((d), (e), (f)) 6
of 13 on the paper
Easy Go to Practice Hub
WDM11/01June 2022 · Edexcel IAL Q2
Critical Path Analysis - Edexcel IAL D1 June 2022 Q2
FRQ 2 of 3 parts ((a), (c)) 8
of 11 on the paper
Medium Go to Practice Hub
WDM11/01June 2022 · Edexcel IAL Q5
Activity Networks & Scheduling - Edexcel IAL D1 June 2022 Q5
FRQ 1 of 4 parts ((b)(iii)) 2
of 9 on the paper
Easy Go to Practice Hub
WDM11/01January 2022 · Edexcel IAL Q4
Critical Path Analysis and Cascade Charts - Edexcel IAL D1 Jan 2022 Q4
FRQ 3 parts ((a), (b), (c)) 10 Medium Go to Practice Hub
WDM11/01October 2021 · Edexcel IAL Q4
Critical path analysis - Edexcel IAL D1 October 2021 Q4
FRQ 2 of 5 parts ((c), (d)) 4
of 11 on the paper
Medium Go to Practice Hub
WDM11/01June 2021 · Edexcel IAL Q2
Critical Path Analysis - Edexcel IAL Decision Mathematics D1 June 2021 Q2
FRQ 2 of 3 parts ((b), (c)) 6
of 10 on the paper
Medium Go to Practice Hub
WDM11/01January 2021 · Edexcel IAL Q6
Critical Path Analysis - Edexcel IAL D1 2021 Jan Q6
FRQ 2 of 5 parts ((d), (e)) 5
of 13 on the paper
Medium Go to Practice Hub
WDM11/01October 2020 · Edexcel IAL Q5
Critical path analysis - Edexcel IAL D1 2020 Jun Q5
FRQ 3 of 4 parts ((b), (c), (d)) 8
of 12 on the paper
Easy Go to Practice Hub
WDM11/01January 2020 · Edexcel IAL Q3
Critical path analysis - Edexcel IAL D1 2020 Jan Q3
FRQ 3 parts ((a), (b), (c)) 9 Medium Go to Practice Hub

Topic question rules and edge cases

How many topic questions cover this syllabus point?
17 question stems cover this subtopic across 15 papers, but only 43 tagged parts and 114 marks belong to it. Other parts of the same questions are assessed under different statements and are excluded from this page.
Which papers include this subtopic?
The table lists every matching session from 2020–2026. Each row links to the question anchor on the paper page, where the full paper context and practice entry point are available.
Why can one question appear under several subtopics?
The parts of one question can assess different syllabus statements. Each part is counted under its own subtopics, so the same question stem can appear on several subtopic pages while each page lists only the parts and marks tagged to that statement.
Can I practise these questions with AI marking?
Yes. Open a paper from the table and use the Interactive Practice Hub entry point. The page itself is static HTML so search engines and retrieval agents can read the full question list without executing JavaScript.